The expected out turn of 12 mm plastering with cement mortar is_______________? September 7, 2025 by Admin A. 2.5 sq m B. 4.0 sq m C. 6.0 sq m D. 8.0 sq m ✅ The correct answer is option D.
The brick work is measured in sq metre, in case of_________________? September 7, 2025 by Admin A. Honey comb brick work B. Brick flat soling C. Half brick walls or the partition D. All the above ✅ The correct answer is option D.
The measurement is not made in square metres in case of________________? September 7, 2025 by Admin A. D.P.C. (Damp proof course) B. Form works C. Concrete Jeffries D. R.C. Chhajja ✅ The correct answer is option D.
The slope of the outlet of ‘P trap’ below the horizontal is kept________________? September 7, 2025 by Admin A. 8° B. 10° C. 12° D. 14° ✅ The correct answer is option D.
If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by_______________? September 7, 2025 by Admin A. Mid-section formula B. Trapezoidal formula C. Prismoidal formula D. All the above ✅ The correct answer is option D.
The correct Prismoidal formula for volume is________________? September 7, 2025 by Admin A. D [first area + last area + Even area + 2 odd areas] B. D/3 [first area + last area + 4 Even area + 2 odd areas] C. D/3 [first area + last area + 2 Even area + 4 odd areas] D. D/6 [first area + odd areas] ✅ The correct answer is option B.
period in a septic tank is assumed___________________? September 7, 2025 by Admin The detention A. 20 minutes B. 25 minutes C. 30 minutes ✅ The correct answer is option C.
The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is____________________? September 7, 2025 by Admin A. 3250 m3 B. 3225 m3 C. 3275 m3 D. 3300 m3 ✅ The correct answer is option B.
The floor area includes the area of the balcony up to_________________? September 7, 2025 by Admin A. 100 % B. 75 % C. 50 % D. 25 % ✅ The correct answer is option C.
If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is___________________? September 7, 2025 by Admin A. B + d + Sd B. Bd + Sd2 C. B × d – Sd1/2 D. ½ (Bd + Sd2) ✅ The correct answer is option B.