(A + B)’s 20 day’s work =
1
x 20
=
2
.
30
3
Remaining work =
1 –
2
=
1
.
3
3
Now,
1
work is done by A in 20 days.
3
Therefore, the whole work will be done by A in (20 x 3) = 60 days.
1
x 20
=
2
.
30
3
Remaining work =
1 –
2
=
1
.
3
3
Now,
1
work is done by A in 20 days.
3
Therefore, the whole work will be done by A in (20 x 3) = 60 days.
10
C’s 1 day’s work =
1
50
(A + B + C)’s 1 day’s work =
1
+
1
=
6
=
3
. …. (i)
10
50
50
25
A’s 1 day’s work = (B + C)’s 1 day’s work …. (ii)
From (i) and (ii), we get: 2 x (A’s 1 day’s work) =
3
25
A’s 1 day’s work =
3
.
50
B’s 1 day’s work
1
–
3
=
2
=
1
.
10
50
50
25
So, B alone could do the work in 25 days.
1
x 8
=
1
.
40
5
Remaining work =
1 –
1
=
4
.
5
5
Now,
4
work is done by Y in 16 days.
5
Whole work will be done by Y in
16 x
5
= 20 days.
4
X’s 1 day’s work =
1
, Y’s 1 day’s work =
1
.
40
20
(X + Y)’s 1 day’s work =
1
+
1
=
3
.
40
20
40
Hence, X and Y will together complete the work in
40
= 13
1
days.
3
3
1
+
1
+
1
=
37
.
8
10
12
120
Work done by P, Q and R in 2 hours =
37
x 2
=
37
.
120
60
Remaining work =
1 –
37
=
23
.
60
60
(Q + R)’s 1 hour’s work =
1
+
1
=
11
.
10
12
60
Now,
11
work is done by Q and R in 1 hour.
60
So,
23
work will be done by Q and R in
60
x
23
=
23
hours 2 hours.
60
11
60
11
So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.
4
(B + C)’s 1 hour’s work =
1
;
3
(A + C)’s 1 hour’s work =
1
.
2
(A + B + C)’s 1 hour’s work =
1
+
1
=
7
.
4
3
12
B’s 1 hour’s work =
7
–
1
=
1
.
12
2
12
B alone will take 12 hours to do the work.
B’s 1 day’s work =
1
.
12
A’s 1 day’s work =
1
; (2 times of B’s work)
6
(A + B)’s 1 day’s work =
1
+
1
=
3
=
1
.
6
12
12
4
So, A and B together can finish the work in 4 days.
1
+
1
+
1
=
15
=
1
.
30
24
20
120
8
Therefore, (A + B + C)’s 1 day’s work =
1
=
1
.
2 x 8
16
Work done by A, B, C in 10 days =
10
=
5
.
16
8
Remaining work =
1 –
5
=
3
.
8
8
A’s 1 day’s work =
1
–
1
=
1
.
16
24
48
Now,
1
work is done by A in 1 day.
48
So,
3
work will be done by A in
48 x
3
= 18 days.
8
8
Then, x + y =
1
and 16x + 44y = 1.
30
Solving these two equations, we get: x =
1
and y =
1
60
60
B’s 1 day’s work =
1
.
60
Hence, B alone shall finish the whole work in 60 days.
n
(A + B + C)’s 1 day’s work =
1
+
1
+
1
=
7
.
24
6
12
24
Formula: If A’s 1 day’s work =
1
,
then A can finish the work in n days.
n
So, all the three together will complete the job in
24
days
=
3
3
days.
7
7
5 : 4 :: 20 : x x =
4 x 20
5
x = 16 days.
Hence, Tanya takes 16 days to complete the work.