142. Work sampling is applied for

[A]. estimation of the percentage utilisation of machine tools
[B]. estimating the percentage of the time consumed by various job activities
[C]. finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible
[D]. all of the above
✅ The correct answer is option D.

143. Dispatching

[A]. prescribes the sequence of operations to be followed
[B]. determines the programme for the operations
[C]. is concerned with the starting of processes
[D]. regulates the progress of job through various processes
✅ The correct answer is option C.