131. A diagram showing the path followed by men and materials while performing a task is known as September 14, 2025 by Admin string diagram flow process chart travel chart flow diagram ✅ The correct answer is option D.
132. In a network shown in the below figure, the critical path is along September 14, 2025 by Admin 1-2-3-4-8-9 1-2-3-5-6-7-8-9 1-2-3-4-7-8-9 1-2-5-6-7-8-9 ✅ The correct answer is option B.
133. The determination of standard time in a complex job system is best done through September 14, 2025 by Admin stop watch time study analysis of micromotions grouping timing technique analysis of standard data system ✅ The correct answer is option D.
134. Which one of the following chart gives simultaneously information about the progress of work and machine loading? September 14, 2025 by Admin Process chart Machine load chart Man-machine chart Gantt chart ✅ The correct answer is option C.
135. Bar chart is suitable for September 14, 2025 by Admin large project major work minor work all of these ✅ The correct answer is option C.
136. PERT analysis is based upon September 14, 2025 by Admin optimistic time pessimistic time most likely time all of these ✅ The correct answer is option D.
137. Which of the following type of layout is suitable for automobile manufacturing concern? September 14, 2025 by Admin product layout process layout fixed position layout combination layout ✅ The correct answer is option A.
138. Military type of organisation is known as September 14, 2025 by Admin line organisation functional organisation line and staff organisation line, staff and functional organisation ✅ The correct answer is option A.
139. Direct expenses include September 14, 2025 by Admin factory expenses selling expenses administrative expenses none of these ✅ The correct answer is option D.
140. In CPM, the cost slope is determined by September 14, 2025 by Admin ✅ The correct answer is option B.