125. PERT requires

single time estimate
double time estimate
triple time estimate
none of these
✅ The correct answer is option C.

126. In a line organisation

responsibility of each individual is fixed
discipline is strong
quick decisions are taken
all of these
✅ The correct answer is option D.

127. Production cost refers to prime cost plus

factory overheads
factory and administration overheads
factory, administration and sales overheads
factory, administration, sales overheads and profit
✅ The correct answer is option A.

128. When slack of an activity is negative

it represents a situation where extra resources are available and the completion of project is not delayed
it represents that a programme falls behind schedule and additional resources are required to complete the project in time
the activity is critical and any delay in its performance will delay the completion of whole project
all of the above
✅ The correct answer is option B.