71. Acceptance sampling is used in job production batch production mass production all of these ✅ The correct answer is option C.
72. Process layout is employed where low volume of production is required where similar jobs are manufactured on similar machines where machines are arranged on functional basis all of the above ✅ The correct answer is option D.
73. When slack of an activity is zero, the activity is critical and any delay in its performance will delay the completion of the whole project. Yes No ✅ The correct answer is option A.
74. The correct sequence of phases in value engineering is creative phase, information phase, investigation phase, evaluation phase information phase, creative phase, investigation phase, evaluation phase investigation phase, information phase, creative phase, evaluation phase creative phase, invest ✅ The correct answer is option A.
75. Slack represents the difference between the earliest completion time and latest allowable time latest allowable time and earliest completion time earliest completion time and normal expected time latest allowable time ✅ The correct answer is option A.
76. Abbreviated work factor data is applied for material handling operation maintenance operation packing and shipping operation all of these ✅ The correct answer is option D.
77. In jobbing production highly skilled workers are needed unit costs are high operations are labour-intensive all of these ✅ The correct answer is option D.
78. In manufacturing management, the term ‘Dispatching’ is used to describe dispatch of sales order dispatch of factory mail dispatch of finished product of the user dispatch of work order ✅ The correct answer is option D.
79. Product layout is used for job production batch production mass production any one of these ✅ The correct answer is option C.
80. Product layout is best suited where one type of product is produced product is standardised product is manufactured in large quantities all of the above ✅ The correct answer is option D.