Industrial Engineering and Production Management MCQs

64. Micromotion study is

analysis of one stage of motion chart
motion study, when seen on a time chart
subdivision of an operation into therbligs and their analysis
enlarged view of motio
✅ The correct answer is option C.

68. When slack of an activity is positive

it represents a situation where extra resources are available and the completion of project is not delayed
it represents that a programme falls behind schedule and additional resources are required to complete the project in time
the activity is critical and any delay in its performance will delay the completion of whole project
any one of the above
✅ The correct answer is option A.

70. CPM requires

single time estimate
double time estimate
triple time estimate
none of these
✅ The correct answer is option A.