81. The main objective of work measurement is to plan and schedule of production formulate a proper incentive scheme estimate the selling prices and delivery dates all of the above ✅ The correct answer is option D.
82. Dummy activities are used to determine the critical path determine the project completion time maintain the required net work none of these ✅ The correct answer is option C.
83. In inventory control, the economic ordering quantity is obtained by the quantity whose procurement cost is equal to inventory carrying cost. TRUE FALSE ✅ The correct answer is option A.
84. The start or completion of task is called an event an activity a duration none of these ✅ The correct answer is option A.
85. The planning and scheduling of job order manufacturing differ from planning and scheduling of mass production manufacturing. Correct Incorrect ✅ The correct answer is option A.
86. Earliest finish time can be regarded as earliest start time + duration of activity earliest start time – duration of activity latest finish time + duration of activity latest finish time – d ✅ The correct answer is option A.
87. The type of layout used for manufacturing steam turbines, is product layout process layout fixed position layout any one of these ✅ The correct answer is option C.
88. The product layout lowers overall manufacturing time requires less space for placing machines utilises machine and labour better all of these ✅ The correct answer is option D.
89. Break even point is the point where fixed and variable cost lines intersect fixed and total cost lines intersect variable and total cost lines intersect sales revenue and tota ✅ The correct answer is option D.
90. A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT). Correct Incorrect ✅ The correct answer is option A.