Industrial Engineering and Production Management MCQs

82. Dummy activities are used to

determine the critical path
determine the project completion time
maintain the required net work
none of these
✅ The correct answer is option C.

86. Earliest finish time can be regarded as

earliest start time + duration of activity
earliest start time – duration of activity
latest finish time + duration of activity
latest finish time – d
✅ The correct answer is option A.

88. The product layout

lowers overall manufacturing time
requires less space for placing machines
utilises machine and labour better
all of these
✅ The correct answer is option D.

89. Break even point is the point where

fixed and variable cost lines intersect
fixed and total cost lines intersect
variable and total cost lines intersect
sales revenue and tota
✅ The correct answer is option D.
Scroll to Top