Prepare with the latest Civil Engineering MCQs with answers and explanations for exams, interviews, and job tests. Our question bank covers key topics including surveying, building materials, structural engineering, geotechnical engineering, fluid mechanics, hydraulics, transportation engineering, environmental engineering, and construction management. These Civil Engineering multiple-choice questions are designed for students, competitive exam aspirants, and professionals preparing for NTS, PPSC, FPSC, PEC exams, university entry tests, and recruitment assessments. Strengthen your knowledge and problem-solving skills with our updated and comprehensive Civil Engineering MCQs.

913. Earliest finish of an activity is always_______________?

A. greater than earliest event time of the following node
B. less than earliest event time of the following node
C. less than or equal to earliest event time of the following node
D. greater than or equal to earliest event time of the following node
✅ The correct answer is option C.