HomeEngineeringIn the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________? 916. In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?By Admin / September 7, 2025 A. longest duration B. highest cost slope C. least cost slope D. shortest duration ✅ The correct answer is option C.