Prepare with the latest Civil Engineering MCQs with answers and explanations for exams, interviews, and job tests. Our question bank covers key topics including surveying, building materials, structural engineering, geotechnical engineering, fluid mechanics, hydraulics, transportation engineering, environmental engineering, and construction management. These Civil Engineering multiple-choice questions are designed for students, competitive exam aspirants, and professionals preparing for NTS, PPSC, FPSC, PEC exams, university entry tests, and recruitment assessments. Strengthen your knowledge and problem-solving skills with our updated and comprehensive Civil Engineering MCQs.

887. In time-cost optimization of a project, crashing is done____________?

A. on all the activities
B. on all the activities lying on the critical path
C. only on activities lying on the orginal critical path and having flatter cost slopes
D. on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
✅ The correct answer is option D.