890. If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is________________? September 7, 2025 by Admin A. 4 days B. 6 days C. 10 days D. 16 days ✅ The correct answer is option D.