$61,000
$71,000
$43,000
$24,000
✅ The correct answer is B.
Actual result = Flexible budget amount + Flexible budget variance
= $57000 + $14000 = $71,000
Actual result = Flexible budget amount + Flexible budget variance
= $57000 + $14000 = $71,000