1341. The basis for determining profit to be taken into account on incomplete contract is ________.

cost of contract
contract price
percentage of work certified as done
uncertified work
✅ The correct answer is C.
The basis for determining profit to be taken into account on incomplete contract is percentage of work certified as done.