✅ The correct answer is option B.
Explanation: After planning is complete, documenting of the plans is done in a Software Project Management Plan(SPMP) document.
✅ The correct answer is option D.
Explanation: Risk management involves anticipating risks that might affect the project schedule or the quality of the software being developed, and then taking action to avoid these risks.
✅ The correct answer is option D.
Explanation: Estimates are based on function points, which are then converted to number of lines of source code. The formula follows the standard form discussed above with a simplified set of seven multipliers.