A project usually has a timeline chart which was developed by_________________?

A. Henry Gantt
B. Barry Boehm
C. Ivar Jacabson
D. None of the mentioned
✅ The correct answer is option A.
Explanation: Timeline chart, also called a Gantt chart was invented by Henry Gantt, an industrial engineer in 1917 .