The critical pressure ratio for gases is September 13, 2025 by Admin 0.528 0.546 0.577 0.582 ✅ The correct answer is option A.
A hollow shaft will transmit a __________ torque than a solid shaft of the same mass and same material. September 13, 2025 by Admin smaller greater ✅ The correct answer is option B.
During cold working process September 13, 2025 by Admin grain structure is distorted strength and hardness of metal increases close dimensional tolerance can be maintained all of the above ✅ The correct answer is option D.
The coriolis component of acceleration is taken into account for September 13, 2025 by Admin slider crank mechanism four bar chain mechanism quick return motion mechanism all of these ✅ The correct answer is option C.
The octane number of petrol, generally available, is September 13, 2025 by Admin 20 to 40 40 to 60 60 to 80 80 to 100 ✅ The correct answer is option D.
In petrol engines, advancing of the spark timing will __________ the knocking tendency. September 13, 2025 by Admin not effect decrease increase ✅ The correct answer is option C.
When a medium carbon steel is heated to coarsening temperature, September 13, 2025 by Admin there is no change in grain size the average grain size is a minimum the grain size increases very rapidly the grain size first i ✅ The correct answer is option C.
In a single stage, single acting reciprocating air compressor, without clearance volume, the workdone is minimum during September 13, 2025 by Admin isothermal compression isentropic compression polytropic compression none of these ✅ The correct answer is option A.
Which of the following bladings will give maximum pressure rise in a centrifugal compressor, assuming the same overall dimensions, blade inlet angle and rotational speeds ? September 13, 2025 by Admin Forward curved blades Backward curved blades Radial blades all of these ✅ The correct answer is option A.
A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is September 13, 2025 by Admin 0.5 0.66 0.84 0.95 ✅ The correct answer is option C.