The correct sequence of phases in value engineering is

creative phase, information phase, investigation phase, evaluation phase
information phase, creative phase, investigation phase, evaluation phase
investigation phase, information phase, creative phase, evaluation phase
creative phase, invest
✅ The correct answer is option A.

When slack of an activity is positive

it represents a situation where extra resources are available and the completion of project is not delayed
it represents that a programme falls behind schedule and additional resources are required to complete the project in time
the activity is critical and any delay in its performance will delay the completion of whole project
any one of the above
✅ The correct answer is option A.