2537. Removal of props under______________? September 7, 2025 by Admin A. slabs spanning upto 4.5 m is 14 days B. beams spanning upto 6 m is 14 days C. slabs spanning upto 4.5 m is 7 days D. All the above ✅ The correct answer is option D.