✅ The correct answer is option B.
Explanation: Functions described in the statement of scope are evaluated and in some cases refined to provide more detail prior to the beginning of estimation.
✅ The correct answer is option D.
Explanation: During the scoping activity decomposition is applied in two major areas: the functionality that must be delivered and the process that will be used to deliver it
✅ The correct answer is option C.
Explanation: To reduce the storage space required by multiple versions of components that differ only slightly, version management systems usually provide storage management facilities.