Software Management MCQs

37. Why is decomposition technique required ?

A. Software project estimation is a form of problem solving
B. Developing a cost and effort estimate for a software project is too complex
C. All of the mentioned
D. None of the mentioned
✅ The correct answer is option C.
Explanation: For these reasons, we decompose the problem, re-characterizing it as a set of smaller problems.

38. Which one is not a risk management activity ?

A. Risk assessment
B. Risk generation
C. Risk control
D. None of the mentioned
✅ The correct answer is option B.
Explanation: Risk management activities would never want a new risk to be generated.

39. Which of the following states that work expands to fill the time available ?

A. CASE tools
B. Pricing to win
C. Parkinson’s Law
D. Expert judgement
✅ The correct answer is option C.
Explanation: The cost is determined by available resources rather than by objective assessment. If the software has to be delivered in 12 months and 5 people are available, the effort required is estimated to be 60 person-months.