1753. Which of the following is a data problem ?

A. hardware problem
B. record organisation problems
C. heavy computational demands
D. loss of comments
✅ The correct answer is option B.
Explanation: Records representing the same entity may be organised differently in different programs.

1755. According to a statistical report: “over 30% of all software projects are cancelled before completion and over 70% of the remainder fail to deliver expected features”. What must be the reason for such a situation ?

A. Poor change management
B. Poor requirements management
C. Poor quality control
D. All of the mentioned
✅ The correct answer is option B.
Explanation: Fundamental to the problem mentioned in the statistical report is poor requirements management. Option a and c are its sub parts.

1756. Which of the following is not a part of process change ?

A. Introducing new practices, methods or processes
B. Introducing new team members to existing project
C. Introducing or removing deliverable
D. Introducing new roles or responsibilities
✅ The correct answer is option B.
Explanation: Adding more developers aid to process completion rather than changing it.