101. Which one of the following techniques is used for determining allowances in time study? Acceptance sampling Linear regression Performance rating Work sampling ✅ The correct answer is option D.
102. Scheduling prescribes the sequence of operations to be followed determines the programme for the operations is concerned with starting of processes regulates the progress ✅ The correct answer is option B.
103. An activity of the project is graphically represented by __________ on the network diagram. a circle a straight line an arrow ✅ The correct answer is option C.
104. Which of the following are the principles of material handling? keep all the handling to the minimum select only efficient handling equipment move the heaviest weight to the least distance all of the above ✅ The correct answer is option D.
105. A company spends considerable amount on publicity to promote sales. This expenditure in break even chart is shown below the fixed cost line variable cost line total cost line sales revenue line ✅ The correct answer is option B.
106. Performance rating is equal to observed performance + normal performance observed performance – normal performance observed performance x normal performance none of the above ✅ The correct answer is option D.
107. The process capability of a machine is defined as the capability of the machine to produce a definite volume of work per minute perform definite number of operations produce job at a definite spectrum of speed hold a definite spectr ✅ The correct answer is option A.
108. Standard time is equal to normal time minus allowances normal time plus allowances representative time multiplied by rating factor normal time taken by a ✅ The correct answer is option B.
109. The unit cost in case of batch production is __________ as compared to jobbing production. same low high ✅ The correct answer is option B.