102. Scheduling

prescribes the sequence of operations to be followed
determines the programme for the operations
is concerned with starting of processes
regulates the progress
✅ The correct answer is option B.

106. Performance rating is equal to

observed performance + normal performance
observed performance – normal performance
observed performance x normal performance
none of the above
✅ The correct answer is option D.

108. Standard time is equal to

normal time minus allowances
normal time plus allowances
representative time multiplied by rating factor
normal time taken by a
✅ The correct answer is option B.