Industrial Engineering and Production Management MCQs

1. Queuing theory is used for

job-shop scheduling
inventory problems
traffic congestion studies
all of these
✅ The correct answer is option D.

3. When slack of an activity is positive

it represents a situation where extra resources are available and the completion of project is not delayed
it represents that a programme falls behind schedule and additional resources are required to complete the project in time
the activity is critical and any delay in its performance will delay the completion of whole project
any one of the above
✅ The correct answer is option A.

5. CPM requires

single time estimate
double time estimate
triple time estimate
none of these
✅ The correct answer is option A.

7. Process layout is employed

where low volume of production is required
where similar jobs are manufactured on similar machines
where machines are arranged on functional basis
all of the above
✅ The correct answer is option D.

9. The correct sequence of phases in value engineering is

creative phase, information phase, investigation phase, evaluation phase
information phase, creative phase, investigation phase, evaluation phase
investigation phase, information phase, creative phase, evaluation phase
creative phase, invest
✅ The correct answer is option A.

10. Slack represents the difference between the

earliest completion time and latest allowable time
latest allowable time and earliest completion time
earliest completion time and normal expected time
latest allowable time
✅ The correct answer is option A.
Scroll to Top