463. What characteristic best describes the cost baseline?

A. Total budget for the project
B. Time phased budget for the project
C. Total budget for the project including the contingency budget
D. Total budget for the project including the contingency budget and the management reserve
✅ The correct answer is option B.

470. A body floats in stable equilibrium________________?

A. when its meatcentric height is zero
B. when the metancentre is above e.g
C. when its e.g. is below it’s center of buoyancy
D. metacentre has nothing to do with position of e.g. for determining stability
✅ The correct answer is option B.