Prepare with the latest Civil Engineering MCQs with answers and explanations for exams, interviews, and job tests. Our question bank covers key topics including surveying, building materials, structural engineering, geotechnical engineering, fluid mechanics, hydraulics, transportation engineering, environmental engineering, and construction management. These Civil Engineering multiple-choice questions are designed for students, competitive exam aspirants, and professionals preparing for NTS, PPSC, FPSC, PEC exams, university entry tests, and recruitment assessments. Strengthen your knowledge and problem-solving skills with our updated and comprehensive Civil Engineering MCQs.

1835. Select the correct statement________________?

A. Quantity of binder required for tack coat is less than that required for prime coat
B. Prime coat treatment is given for plugging the voids in water bound macadam during bituminous road construction
C. Seal coat is the final coat over certain previous bituminous pavements
D. A bitumen primer is a high viscosity cutback
✅ The correct answer is option D.