31. Cost of fittings and their fixing is specified for the following sanitary fittings________________? A. Water closets B. Flushing pipes C. Lavatory basins D. All the above ✅ The correct answer is option D.
32. The damp proof course (D.P.C.) is measured in________________? A. Cub. m B. Sq. m C. Metres D. None of these ✅ The correct answer is option B.
33. The expected out turn for earth work in excavation in ordinary soil per workman per day is_______________? A. 1.00 cum B. 2.00 cum C. 3.00 cum D. 4.00 cum ✅ The correct answer is option C.
34. Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds_________________? A. 2.0 % B. 2.5 % C. 4.0 % D. 5.0 % ✅ The correct answer is option D.
35. The item of the brick structure measured in sq.m, is___________________? A. Reinforced brick work B. Broken glass coping C. Brick edging D. Brick work in arches ✅ The correct answer is option B.
36. The expected out turn of 2.5 cm cement concrete floor per mansion per day__________________? A. 2.5 sqm B. 5.0 sqm C. 7.5 sqm D. 10 sqm ✅ The correct answer is option C.
37. In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and_________________? A. Breadth of the wall B. Half breadth of wall on each side C. One fourth breadth of wall on each side D. None of these ✅ The correct answer is option B.
38. Anti-siphonage pipe is connected to__________________? A. Main soil pipe B. Bottom of P trap W.C. C. Top of P trap W.C. D. Side of water closet ✅ The correct answer is option C.
39. For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is_______________? A. 0.90 m3 B. 0.94 m3 C. 0.98 m3 D. 1.00 m3 ✅ The correct answer is option B.
40. For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is___________________? A. 0.200 m3 B. 0.247 m3 C. 0.274 m3 D. 0.295 m3 ✅ The correct answer is option C.