121. A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
Whole work is done by A in
20 x
5
= 25 days.
4
Now,
1 –
4
i.e.,
1
work is done by A and B in 3 days.
5
5
Whole work will be done by A and B in (3 x 5) = 15 days.
A’s 1 day’s work =
1
, (A + B)’s 1 day’s work =
1
.
25
15
B’s 1 day’s work =
1
–
1
=
4
=
2
.
15
25
150
75
So, B alone would do the work in
75
= 37
1
days.
2
2