HomeEngineeringIn the penetration macadam construction, the bitumen is__________________? 1764. In the penetration macadam construction, the bitumen is__________________?By Admin / September 7, 2025 A. sprayed after the aggregates are spread and compacted B. premixed with aggregates and then spread C. sprayed before the aggregates are spread and compacted D. none of the above ✅ The correct answer is option A.