indirect wages
health wages
idle time wages
shortage time wages
✅ The correct answer is C.
In costing of project, wages paid to workers for unproductive work at time of material shortage is termed as idle time wages. The labour cost of normal idle time may be treated as an item of factory expenses and recovered as an indirect charge in case of indirect workers.