1915. If the R.L’s of canal bed level and high flood level of drainage are 212.0 m and 210.0 m respectively, then cross drainage work will be________________? September 7, 2025 by Admin A. aqueduct B. superpassage C. syphon D. syphon aqueduct ✅ The correct answer is option C.