14000 units
14500 units
15000 units
15500 units
✅ The correct answer is A.
Reorder point = Number of units sold × Purchase order lead time
= 400 × 35 = 14000 units
Reorder point = Number of units sold × Purchase order lead time
= 400 × 35 = 14000 units