A. $40,000
B. $50,000
C. $150,000
D. $170,000
✅ The correct answer is option A.
Flexible budget cost = Flexible budget variance – Actual cost
= $105000 – $65000
= $40000.
Flexible budget cost = Flexible budget variance – Actual cost
= $105000 – $65000
= $40000.