3281. If direct material cost is $85000 and direct manufacturing labour is $25000, then prime cost would be

$13,500
$55,600
$60,000
$110,000
✅ The correct answer is D.
Prime cost = Direct material cost + Manufacturing labour
= $85000 + $25000 = $110,000