1. If direct material cost is $5500 and prime cost is $25000, then direct manufacturing labour would be August 24, 2025 by Administrator A) $19,500 B) $30,500 C) $45,500 D) $22,500 ✅ ANSWER: A Direct manufacturing labour = Prime cost – Direct material cost = $25000 – $5500 = $19,500