114. If actual price input is $500, budgeted price of input is $300 and actual quantity of input is 50 units, then price variance would be

A. $4,000
B. $6,000
C. $8,000
D. $10,000
✅ The correct answer is option D.
Price variance = (actual price input – budgeted price of input) × Actual quantity of input
= ($500 – $300) × 50 = $10,000.