$55,000
$37,500
$95,000
$26,000
✅ The correct answer is C.
Prime cost = Direct material cost + Direct manufacturing labour
= $75000 + $20000 = $95,000
Prime cost = Direct material cost + Direct manufacturing labour
= $75000 + $20000 = $95,000