2007. Considering dual rate method, if employees work for 8500 budgeted hours at $120 per hour and work for 9500 actual hours at $110 per hour, then total cost would be

$2,078,000
$3,078,000
$2,065,000
$3,065,000
✅ The correct answer is C.