111. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

[A]. Rs. 375
[B]. Rs. 400
[C]. Rs. 600
[D]. Rs. 800
✅ The correct answer is option B.
C’s 1 day’s work =
1

1
+
1

=
1

7
=
1
.

3
6
8
3
24
24

A’s wages : B’s wages : C’s wages =
1
:
1
:
1
= 4 : 3 : 1.

6
8
24

C’s share (for 3 days) = Rs.

3 x
1
x 3200

= Rs. 400.

24