HomeEngineeringA PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 17625. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days isBy Admin / September 13, 2025 0.5 0.66 0.84 0.95 ✅ The correct answer is option C.