HomeEngineeringWhen slack of an activity is zero, the activity is critical and any delay in its performance will delay the completion of the whole project. 11741. When slack of an activity is zero, the activity is critical and any delay in its performance will delay the completion of the whole project.By Admin / September 8, 2025 Yes No ✅ The correct answer is option A.