SPMP stands for__________________?

A. Software Project Manager’s Plan
B. Software Project Management Plan
C. Software Product Management Plan
D. Software Product Manager’s Plan
✅ The correct answer is option B.
Explanation: After planning is complete, documenting of the plans is done in a Software Project Management Plan(SPMP) document.

Risk management is one of the most important jobs for a__________________?

A. Client
B. Investor
C. Production team
D. Project manager
✅ The correct answer is option D.
Explanation: Risk management involves anticipating risks that might affect the project schedule or the quality of the software being developed, and then taking action to avoid these risks.