CG Co manufactures a single product T. Budgeted production output of product T during June is 200 units. Each unit of product T requires 6 labour hours for completion and CG Co anticipates 20 per cent idle time. Labour is paid at a rate of Rs7 per hour. The direct labour cost budget for March is

Rs. 6,720
Rs. 8400
Rs. 10080
Rs. 10500
✅ The correct answer is D.
For every 100 hours that they pay for, there are 20 hours idle and therefore 80 hours worked.
So, for every 80 hours worked they will have to pay for 100 hours, again with 20 hours idle.

The idle time is 20/80 = 25% of the time worked.

So for this question they need 200 x 6 = 1200 hours of work.
Therefore they will have to pay for 1200 x 100/80 = 1500 hours.
This will cost them 1500 x Rs. 7 = Rs.10,500

In activity based costing method implementation, an output unit level costs are classified as

indirect costs
direct cost
labour cost
raw material cost
✅ The correct answer is A.
In activity based costing method implementation, an output unit level costs are classified as indirect costs. Indirect costs are costs used by multiple activities, and which cannot therefore be assigned to specific cost objects.

“During September, 300 labour hours were worked for a total cost of Rs. 4800 The variable overhead expenditure variance was Rs. 600 (A) Overheads are assumed to be related to direct labour hours of active working. What was the standard cost per labour hour?”

Rs. 14
Rs. 1650
Rs. 1750
Rs. 18
✅ The correct answer is A.
Total Cost 4800
Variance was Rs. 600 (A)
As Variance adverse means it is higher than standard cost
So standard cost = 4800 – 600 = 4200
Labour worked 300 hours
Standard cost per labour hour = 4200/300 =14

In an activity based cost system; an activity/unit of work or task with differentiated purposes will be classified as

different task
purpose cost
an activity
an allocation cost
✅ The correct answer is C.
In an activity based cost system; an activity/unit of work or task with differentiated purposes will be classified as an activity. Activity-based costing (ABC) is an accounting method that identifies and assigns costs to overhead activities and then assigns those costs to products.

The cost per unit of a product manufactured in a factory amounts to Rs 160 (75% variable) when the production is 10,000 units. When production increases by 25%, the cost of production will be Rs per unit.

Rs 145
Rs 150
Rs 152
Rs 140
✅ The correct answer is C.
Cost p.u 160

75%is variable cost 120p.u

40rs p.u fixed cost (fixed cost not change when production unit increase or decrease) fixed cost is
40 * 10000 = Rs. 400000

Cal cost p.u if production increase by 25%

10000 + 25% = Rs. 12500

Total cost = variable cost + fixed cost

(12500 * 120) + 400000 = Rs. 1900000

Cost p.u = 1900000 / 12500 = Rs. 152

A document which consists information about labour time usage, for specific job in a specific department, is known as

selling time record
labour time record
buying time record
direct time record
✅ The correct answer is B.
A document which consists information about labour time usage, for specific job in a specific department, is known as labour time record. A document which records the amount of time spent by an employee, showing the analysis between a numbers of activities during a payment period. It may record the wages (labour cost) of the time spent.