[A]. 5 5 11
[B]. 5 6 11
[C]. 6 5 11
[D]. 6 6 11
✅ The correct answer is option A.
P can complete the work in (12 x 8) hrs. = 96 hrs.
Q can complete the work in (8 x 10) hrs. = 80 hrs.
P can complete the work in (12 x 8) hrs. = 96 hrs.
Q can complete the work in (8 x 10) hrs. = 80 hrs.
P’s1 hour’s work =
1
and Q’s 1 hour’s work =
1
.
96
80
(P + Q)’s 1 hour’s work =
1
+
1
=
11
.
96
80
480
So, both P and Q will finish the work in
480
hrs.
11
Number of days of 8 hours each =
480
x
1
=
60
days = 5
5
days.
11
8
11
11