Practice the latest Mathematics MCQs with answers and explanations to excel in exams, interviews, and job tests. Our collection covers algebra, calculus, geometry, trigonometry, statistics, probability, arithmetic, matrices, and differential equations. These Mathematics multiple-choice questions are designed for students, competitive exam aspirants, and professionals preparing for NTS, PPSC, FPSC, CSS, PMS, university entry tests, and recruitment assessments. Strengthen your problem-solving skills, improve accuracy, and boost your exam performance with our updated Mathematics MCQs.

338. C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?

A. 10 days
B. 12 days
C. 8 days
D. 9 days
✅ The correct answer is option A. 10 days.
Part of work completed by C in 1 day = 1/12 Part of work completed by D in 1 day = 1/15 Part of work completed by C in 4 days

= 1/3 Work remaining = 2/3 Time taken by D to complete the work

= (2/3)÷(1/15) = 10 days