63. PM-CMM stands for___________________?

A. people management capability maturity model
B. process management capability maturity model
C. product management capability maturity model
D. project management capability maturity model
✅ The correct answer is option A.
Explanation: The people management maturity model defines the following key practice areas for software people: recruiting, selection, performance management, training, compensation, career development, organization and work design, and team/culture development

64. What threatens the quality and timeliness of the software to be produced ?

A. Known risks
B. Business risks
C. Project risks
D. Technical risks
✅ The correct answer is option D.
Explanation: Technical risks identify potential design, implementation, interface, verification, and maintenance problems.

67. Which of the following are parameters involved in computing the total cost of a software development project ?

A. Hardware and software costs
B. Effort costs
C. Travel and training costs
D. All of the mentioned
✅ The correct answer is option D.
Explanation: All these are accounted for in estimating a software development cost

68. A software ______________ provides the framework from which a comprehensive plan for software development can be established?

A. people
B. product
C. process
D. none of the mentioned
✅ The correct answer is option C.
Explanation: A small number of framework activities are applicable to all software projects, regardless of their size or complexity.