1672. The intent of project metrics is_____________________?

A. minimization of development schedule
B. for strategic purposes
C. assessing project quality on ongoing basis
D. minimization of development schedule and assessing project quality on ongoing basis
✅ The correct answer is option D.
Explanation: A project metric is a quantitative measure of the degree to which a system, component or process possesses an attribute.

1674. In CMM, the life cycle activities of requirements analysis, design, code, and test are described in_________________________?

A. Software Product Engineering
B. Software Quality Assurance
C. Software Subcontract Management
D. Software Quality Management
✅ The correct answer is option A.
Explanation: In CMM planning these activities is described in Software Project Planning, however the life cycle activities of requirements analysis, design, code, and test are described in Software Product Engineering.

1680. When does one decides to re-engineer a product ?

A. when tools to support restructuring are disabled
B. when system crashes frequently
C. when hardware or software support becomes obsolete
D. subsystems of a larger system require few maintenance
✅ The correct answer is option C.
Explanation: Re-engineering involves putting in the effort to make the system easier to maintain