123. How is WINWIN Spiral Model different from Spiral Model ?

A. It defines tasks required to define resources, timelines, and other project related information
B. It defines a set of negotiation activities at the beginning of each pass around the spiral
C. It defines tasks required to assess both technical and management risks
D. It defines tasks required to construct, test, install, and provide user support
✅ The correct answer is option B.
Explanation: Except option “b” all other tasks/activities are present in Spiral Model as well.

129. What is MTTF ?

A. Maximum time to failure
B. Mean time to failure
C. Minimum time to failure
D. None of the mentioned
✅ The correct answer is option B.