1012. How is throwaway prototype different from evolutionary prototype ?

A. It involves successive steps
B. It involves just one task
C. The prototype is built with the idea that it will eventually be converted into final system
D. It has a shorter development time
✅ The correct answer is option B.
Explanation: Except option b all other options represent the characteristics of an evolutionary prototype

1014. The 4GT Model is a package of _________________?

A. CASE Tools
B. Software tools
C. Software Programs
D. None of the mentioned
✅ The correct answer is option B.
Explanation: 4GT encompasses a broad array of software tools enabling the software engineer to specify the characteristics at a high level leading to an automatically generated source code based on these specifications.