Construction Planning and Management MCQs

43. Crash project duration is obtained by summing the________________?

A. normal durations for all the activities
B. crash durations for all activities
C. crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
D. crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
✅ The correct answer is option D.

44. Whenever an activity has zero total float, then_______________?

A. free float of the activity must be zero but independent float need not be zero
B. independent float must be zero but free float need not be zero
C. free float and independent float both must be zero
D. free float and independent float both need not be zero
✅ The correct answer is option C.